string(1) "1"

INTERCONEXION MAD-4

Data Processing Centre

  • Promoter: Interxion
  • Date: 2022-2023
  • Location: Madrid (Spain)
  • Service: Construction consultancy and PMO
  • Subservice: BIM Managemen
  • Challenge
  • Our work

Challenge

With 29,460 square meters and 6 floors, the INTERXION MAD4 data processing center is the largest in the capital, with a capacity of 34 MW of power and the capacity to store 140,000 servers.

The work has a budget of 230 millions.

Our work

Ayesa collaborates in the generation of the As-Built model of the diesel installations that are used to cool the servers in the case of a failure.

We support your projects

Our goal is to provide you with the best services for your needs

Making it happen