Challenge
The project includes two buildings for Data Processing Centres, each DC consisting of a service building and a module with two IT rooms on the same floor (approx. 1,400 m²) and an electrical room.
Functional requirements:
- Connections between the modules and service buildings.
- Accessibility to IT, power supply and cooling equipment.
- Specific study of the cooling of the IT rooms using Computational Fluid Dynamics (CFD) analysis comprising a modelling of the morphology of the room and progressive calculations.
- Each building will contemplate the future extension of a module with two IT
rooms of the same surface area, in addition to an electrical room.
- TIER III certification by the Uptime Institute, without prejudice to the fact that the design incorporates TIER IV functionalities.
Our work
Ayesa participated in all phases of this large data centre, from conceptual design to handover, including all Riba stages 2 to 5 of the design process and construction management of the works.