Detail Engineering for new Lixiviation Pre-reactor in the Las Cruces hydro-metallurgic copper plant

Detail engineering of a leaching reactor at the Las Cruces Copper Works in Seville. 

To increase the recovery of copper, the need to raise the residence time of the acid pulp in the leaching process was considered, including in line a new super duplex stainless steel leaching tank.

A design was drawn up for finite elements of the super-duplex stainless steel tank, with stirrer and hydraulic stamp in accordance with regulation API 650, as well as the connection of the various lines (cold refining, hot refining, oxygen, pulp, etc.) with the rest of the installation. The design includes equipment selection, implementation, removal of the current installations by 3D scanner, 3D design of the new isometrics, supports and calculation of corrosive/abrasive fluid stress on steel and FRP piping at high temperatures. 

The new installation was implemented whilst the plant continued to operate.

Scope was increased, with the addition of subsequent work supervision and technical construction management. 

News

Ayesa comes top in the VII Awards for the Best Practices  in Sustainable Mobility
02/10/2019

Ayesa comes top in the VII Awards for the Best Practices in Sustainable Mobility

CEO: ‘Andalusia needs a portfolio of major investment projects to compete at an international level’
23/09/2019

CEO: ‘Andalusia needs a portfolio of major investment projects to compete at an international level’

Ayesa in 2018: 1.5% growth, 274 million euros in revenue and 24 million euros in EBITDA
13/05/2019

Ayesa in 2018: 1.5% growth, 274 million euros in revenue and 24 million euros in EBITDA

New edition of INGENIO, our corporate magazine
15/03/2019

New edition of INGENIO, our corporate magazine

“Industry must be bolstered in 4.0 environments to tackle the disruptive changes in the offing”
03/01/2019

“Industry must be bolstered in 4.0 environments to tackle the disruptive changes in the offing”

EQO contracts Ayesa to transform its chlorine plant
30/10/2018

EQO contracts Ayesa to transform its chlorine plant