Simple Circuit AT airline project with 2 conductors per phase, to connect the Dominica Wind Farm substation with 200MW generation capacity, with the transport network located in Charcas Substation (CFE).
The line has a length of 39 km. It has been designed and calculated according to the requirements and specifications of CFE.

Features:

  • Nominal Voltage: 115kV, 60Hz
  • LAT driver: ACSR / AS 1113
  • Guard wire OPGW 12 Fibers (12 fibres G.652)
  • Number of towers: 147
  • Lattice metal structure towers
Location
Mexico

News

Ayesa in 2018: 1.5% growth, 274 million euros in revenue and 24 million euros in EBITDA
13/05/2019

Ayesa in 2018: 1.5% growth, 274 million euros in revenue and 24 million euros in EBITDA

New edition of INGENIO, our corporate magazine
15/03/2019

New edition of INGENIO, our corporate magazine

“Industry must be bolstered in 4.0 environments to tackle the disruptive changes in the offing”
03/01/2019

“Industry must be bolstered in 4.0 environments to tackle the disruptive changes in the offing”

EQO contracts Ayesa to transform its chlorine plant
30/10/2018

EQO contracts Ayesa to transform its chlorine plant

Ayesa is awarded its third contract to adapt a Spanish port for new LNG logistics services
06/09/2018

Ayesa is awarded its third contract to adapt a Spanish port for new LNG logistics services

Spanish engineering for Japanese nylon
29/08/2018

Spanish engineering for Japanese nylon