Power lines and substations

High voltage line design to connect the Wind Farm Dominicana

Simple Circuit AT airline project with 2 conductors per phase, to connect the Dominica Wind Farm substation with 200MW generation capacity, with the transport network located in Charcas Substation (CFE).
The line has a length of 39 km. It has been designed and calculated according to the requirements and specifications of CFE.

Features:

  • Nominal Voltage: 115kV, 60Hz
  • LAT driver: ACSR / AS 1113
  • Guard wire OPGW 12 Fibers (12 fibres G.652)
  • Number of towers: 147
  • Lattice metal structure towers
Location
Mexico

News

José Luis Manzanares Abásolo, CEO of Ayesa, Engineer of the Year 2019
26/11/2019

José Luis Manzanares Abásolo, CEO of Ayesa, Engineer of the Year 2019

Ayesa comes top in the VII Awards for the Best Practices  in Sustainable Mobility
02/10/2019

Ayesa comes top in the VII Awards for the Best Practices in Sustainable Mobility

CEO: ‘Andalusia needs a portfolio of major investment projects to compete at an international level’
23/09/2019

CEO: ‘Andalusia needs a portfolio of major investment projects to compete at an international level’

Ayesa in 2018: 1.5% growth, 274 million euros in revenue and 24 million euros in EBITDA
13/05/2019

Ayesa in 2018: 1.5% growth, 274 million euros in revenue and 24 million euros in EBITDA

New edition of INGENIO, our corporate magazine
15/03/2019

New edition of INGENIO, our corporate magazine

“Industry must be bolstered in 4.0 environments to tackle the disruptive changes in the offing”
03/01/2019

“Industry must be bolstered in 4.0 environments to tackle the disruptive changes in the offing”